|
|
Home | Contact Us | Press Room | Site Overview | Help | Login | Register |
![]() |
![]() |
| About NCSL | State & Federal Issues | Legislatures | Legislative Staff | Meetings | Bookstore | Legislators & Staff Only |
| NCSL Home > Legislative Staff: Staff Sections & Networks > NLPES > | Add to MyNCSL |
NLPES
Site Map
NLPES Question of the MonthJanuary 2001What steps do you take to ensure that your projects finish on time?From: Jeanne Jarrett, Missouri In Missouri's Oversight Division, we establish estimated hours to complete
projects, but only as a planning tool. By statute, we have one year
from the date assigned in which to complete evaluations. If we don't
complete them within the year, we must ask our governing committee, the
Committee on Legislative Research, for an extension of time to complete
the project. This has happened twice within the past seven years,
but because of unusual circumstances. We do our best to complete
evaluations by January of each year in order to present the information
to the legislature at the beginning of the legislative session. We
have a series of meetings throughout the course of an evaluation for the
purpose of keeping focused and addressing issues quickly. The first
is a brainstorming meeting with the team assigned to do the evaluation.
We usually have two or three progress meetings along the way to address
where we're at in the project and whether we are on target to meet deadlines.
The Director, Team Leader and Team Members all attend these meetings. If
a project is dragging, we can usually identify the causes early and adjust
resources or strategy.
From: Shan Hays, Arizona In Arizona, we have a pretty structured approach. At the beginning of our 2-year cycle, we do some advance work and estimate how many hours we'll need for each project. We then allocate the projects among our teams, based on the number of hours the team has available, team preferences, expertise, etc. Each team is responsible for figuring out how to allocate staff and calendar time to get its set of audits done by the deadlines. Budget hours for each project vary from about 500-4,500, but the typical project is probably around 2,500 hours. We have targets for allocating the budget between the 3 major phases of the project: preliminary survey (20%), fieldwork (50% for smaller projects, 55% for larger ones), and report writing/processing (30% for smaller projects, 25% for larger ones). We set these guidelines in 1997 after doing a study that found that most audits that went over 25% in preliminary survey ended up going over budget. At the beginning of the project, the senior lays out a rough calendar, based on the size of the team and the budget. These dates are usually treated as targets, not cast in stone. However, later, near the end of fieldwork, we put together a detailed schedule for all the stops along the report review process for each report. We do this on a spreadsheet. This lets us make sure the editor, secretary, etc. don't get a stack of reports all at once. These are the mechanics of scheduling. We do lots of other things designed to make our work more efficient, so we can actually complete the work in the hours budgeted. For example, we have a "lessons learned" process where we assess what we could have done differently; we consider every methods decision in light of how much time and budget we have; we try to staff projects with the right mix of people; we double up on supervision so things can run concurrently; share staff among teams when we need to, and so on. No matter how well we plan, we still run into things like agency data
problems that double the time it takes to complete a project. Still,
having a plan in place for the remaining projects lets us minimize the
overall impact of these problems.
From: Jane Thesing, South Carolina We establish a budget for each audit when we have completed our survey work and have developed the audit plan. The budget is stated in total hours and target dates are calculated for each step of the audit process (fieldwork, draft report, management review, exit, etc.). Target dates are also established for each auditor for each section of the audit plan. We monitor those dates as we progress. If it appears that we are not going to meet our target dates, we consider the significance of the situation. If having the audit published by a certain date is important to the General Assembly or to the members who requested it, we make adjustments to enable us to complete it on time. One adjustment is to shorten the in-house review time scheduled. For example, normally management would have a week to review a draft report. If time were of the essence, the manager could ask the other managers to review the draft in a day or two. Another adjustment is to drop less material/significant areas of the plan or narrow the scope of the fieldwork areas that have yet to be completed. This involves a tradeoff, but we have to do some hard thinking and consider whether the General Assembly/State would rather have the main essence of the work sooner or the entire product later. Also, staff commonly put in extra hours (not required) to expedite the work. If having the audit published by a certain date is not of concern to
the General Assembly or to the members who requested the audit, and the
audit objectives are considered significant, we would continue and complete
the plan, adjusting the target dates (we don't adjust the budget in hours
and continue to record our hours, so there is a record of how much time/money
the audit took compared to the original plan). Improving our timeliness
is a goal we are always working with, so I look forward to reading suggestions
from everyone else!
From: Rachel Cohen, Texas The key steps we take to help ensure that projects get done on time include:
If it becomes clear, despite our best efforts, that the original deadline cannot realistically be met, we will extend the deadline if it is possible to do so. These "extensions" are rare, and are usually only for one month. From: Ken Levine, Texas Sunset Advisory Commission
In Michigan, we have not yet discovered the secret for finishing projects
on time. We do use a detailed project budgeting and project tracking
system. We find it to be of considerable value, both in attempting
to finish projects on time and to plan workflow and staff assignments.
However, it certainly does not result in all projects being completed on
time!
From: Joel Alter, Minnesota The large majority of program evaluations done by our office are issued during the early weeks of the legislative session—typically in January or February. Reports issued later in the session may miss their opportunity to have an impact, and reports issued when the Legislature is not in session may be “old news” by the time the Legislature meets again. Aside from setting milestone target dates for key points in each study, our project scheduling approach is fairly informal. The Deputy Legislative Auditor determines how many staff to assign to each project based on a general notion of project size. Most of our projects start and end at roughly the same time, so a project with four people assigned to it should be able to accomplish a lot more than a project with two staff. We track the total hours consumed by each project (and by several project phases, such as “research” and “report preparation”)—but project deadlines are the main tool used to track project timeliness, rather than comparisons of projected and actual hours used. Each project manager sets target dates for the project workplan, outline of findings, internal draft, closing conference, and report release. Also, each manager prepares biweekly status reports for the Legislative Auditor and Deputy Legislative Auditor. These reports indicate activities of project staff in the previous two weeks and priorities for the upcoming two weeks—as well as any changes in the key target dates. Project staff meet monthly with the Legislative Auditor and Deputy Legislative Auditor to discuss the status of the project and its schedule. Our support staff prepare a timeline for each manager—working backwards from the release date to the date when project staff have completed an internal draft. This timeline includes interim deadlines for the last few weeks of the project—including things like when sidebars should be inserted in the report and when mailing labels should be prepared for report distribution. Despite these efforts, we have still had mixed success issuing reports that meet our internal deadlines. |
© 2008 National Conference of State Legislatures, All Rights Reserved
Denver Office: Tel: 303-364-7700 | Fax: 303-364-7800 | 7700 East First Place | Denver, CO 80230 | Map
Washington Office: Tel: 202-624-5400 | Fax: 202-737-1069 | 444 North Capitol Street, N.W., Suite 515 | Washington, D.C. 20001